1916 The BASF begins in May under
the pressure of the war ministry with the construction of an ammoniated work
to the production of saltpetre or nitric acid on the area between Merseburg
and Spergau to secure the explosive care for the continuation of the First
World War and the fertilizer care of the agriculture.
1917 After only eleven-month
construction time the first ammoniated synthesis stove is started in the "
ammoniated work of Merseburg " (late Leuna works). On the 29th April, 1917
the first tankers with watery ammoniated solution left the work. The first
post processing arrangements to the production of ammonium sulphate
fertilizer were established.
1918 By the material battles
becoming harder and harder the uppermost army management feels constrained
to extend the production capacity in ammonia. The imperial Treasury and the
BASF sign a contract to the other removal of the work on 250,000 t of
ammonia per year.
1919 After the First World War the
allies demand the dismantling of the Leunaer ammoniated synthesis
arrangements whose construction had been released only by the war. Carl
Bosch prevents the destruction of the arrangements in which he persuades the
French side of the fact that the ammoniated factories of Germany are for the
fertilizer production and with it the food of eminent meaning. A smoking
chimney and a grain ear cruising him become the company logo of the Leuna
works.
1921 The demands for higher wages,
regulated working hours, removal of the extra hours and Sunday work,
introduction and recognition of works committees, uniform care and correct
treatment by superiors leads already since 1917 to several strikes. The
general strike from the 23rd March to the 19th April led to the occupation
of the work by armed workers and to the March fights.
1922 The most important research
companies and test companies of the BASF are shifted by Ludwigshafen to
Leuna. The works concentrate upon other applications of catalytic
high-pressure procedures.
1923 From Alwin Mittasch and
Christian Schneider in Ludwigshafen the developed second big technical
high-pressure synthesis, the synthesis of methanol from carbon monoxide and
hydrogen, is realised under the direction of Matthias Pier. With this
synthesis Leuna is the only work in the world which can produce methyl
alcohol on synthetic way at this time.
1925 With the foundation of the
group "IG Farbenindustrie AG" becomes Carl Bosch Vorstandsvorsitzender of
this immense enterprise and contributes with his decisions substantially to
the other development Leunas. Matthias Pier develops in the same year the
procedure carried out in 1913 for the first time by Friedrich Bergius to the
coal hydrogenation under use of catalysts.
1926 On the base of the present
knowledge from lab test results the decision is met for the construction of
a great experimental plant with a capacity of 100,000 metric tons of petrol
per year. This is with decisively for the development of the merchant's
generators which play a big role as a heart of the hydrogen production for
the Hydrierverfahren in Leuna.
1927 The introduction of the first
two-stage brown coal hydrogenation arrangement with which was aimed at
generating petrol, light oil and lubricating oil from the home brown coal,
however, also from tar and heavy oil factions by means of hydrogen under
pressure.
1929 With the stock market collapse
in the New York Wall Street the world falls in an economic and financial
crisis of the biggest magnitude which has dramatic consequences, above all,
in the leading industrial lands. The ammoniated production goes back to
approx. 30%, 66% of all employees in the location must be dismissed.
1933 The autarky attempts of the
National Socialists lead to the end of the so-called "petrol contract"
between the German empire and the Ammonikwerk Merseburg. The contract allows
the large-scale technical removal of the high-pressure coal hydrogenation to
cover the growing fuel need for civil and military purposes.
1934 The main focus of the work
development lies on the production of special fuels and oils. The capacities
of hdydration are extended constantly and increased in her efficiency.
1936 The petrol renderer
distillation takes up the production of airplane petrol. Because of the
increasing need of the new production plants in electric energy it is begun
with the assembly of high-pressure kettles.
1937 Introduction of the isooctane
arrangement to the production of hit resistent fuels. The Leuna factory is
distinguished on the world exhibit in Paris for the chemical-technical
achievements in the area of the high-pressure procedures with the Grand
Prix.
1939 Removal of the arrangements to
the saltpetre fertilizer production with the purpose of an increase of 50 t
of N per day. An arrangement to the production of adipic acid is put into
operation. The war-economic requirements determine stronger and stronger the
production.
1941 Introduction of a new great
arrangement to production of airplane petrol by dehydration of Isobutan.
Establishment of a great arrangement to the production of Caprolactam.
1943 Introduction of the At
procedure to the alkylation of Isobutan with n-Buten. The DHD arrangement (Reforming
of petrol in molybdenum catalysts) is put into operation. The production of
Düngemitteln is very falling, because more and more ammonia to nitric acid
is processed by the quickly rising explosive consumption.
1944 At the middle of May the first
heavy air raid on Leuna occurs. The construction achievements and repair
achievements to the resumption of the production in the damaged arrangements
accept unusual magnitudes.
1945 After 22 air raids the Leuna
factory was hard destroyed at the beginning of the year and offered a
picture of the devastation. After the last air raid on 04.04.1945 the
production comes to a great extent for succumbing. The work is taken at the
middle of April by the American troops which are removed at the beginning of
July from Soviet troops. The hydrogenation takes up the production again.
1946 Big parts of the factory are
dismantled from the middle of March according to the regulations of the
Potsdam agreement. 43 experts from all areas are obliged to several years'
work in the Soviet Union. The crossing in Soviet property as a Soviet
corporation (SAG) for mineral fertilizer from July the setting of the
dismantlings entails. The reconstruction plan worked out by the German work
management is tackled under extreme difficulties.
1947 In the ammoniated factory the
first stove chambers go to company again, the production of Mersol and
Mersolat is taken up and the production of Isobutylöl and methanol
stabilises.
1949 A chamber to the tar
hydrogenation is put into operation again.
1951 Beginning of the crossing of
the coal hydrogenation for the oil processing. In the hydrogenation Austrian
crude oil (matzoes) is used.
1952 The tar processing is put, a
small-technical arrangement to the catalytic cracking takes up the company.
1954 The LeunaWerk as the biggest
and most important chemical company will hand over together with 32 other
SAG to companies to the GDR.
1958 In the chemical conference on
the 3rd/4th of November in Leuna a program which intends the duplication of
the production of the chemical industry is decided. Beside the removal of
the traditional Carbochemie the petrolchemische complex (Leuna factory II)
counts to the most important new building plans.
1959 The last coal hydrogenation
arrangement is taken except company. The construction of the investment
complex of Leuna II begins. In the period till 1971 two petrol split-blocks
originate to the Ethylenerzeugung, guest racing arrangements to the
isolation of methane, Propylen, Olefinen and other products, the
Hochdruck-Polyethylenanlage, C arrangements to the production of Caprolactam
of phenol and to the utilization of by-products.
1967 In the course of the combine
education the Leuna work to the minister for chemical industry is
subordinated directly. The oil pipeline Schwedt - Leuna is put into
operation and forms with it the base for the care of the petrolchemischen
complex with the required oil.
1971 Bigger capital projects like
the construction of the industrial power station the north, the new oxygen
factory, the reconstruction of the synthesis gas production, the oil
processing and the extension of the Mirathen production have, above all, the
increase of the production to the purpose.
1973 With completion of the natural
gas management, except the Leuna works also the Poles VR, the Hungarian VR
and them and *268; supplying SSR with Soviet natural gas, not only a new raw
material spring is opened, but also a determining improvement of the terms
of employment and environmental conditions is reached. The first
Hydrospaltkammer takes up the continuous operation.
1975 Introduction of the
Ethylen-group management with Böhlen and extension of the production
capacities by realisation of important investments in the IKW north, the
natural gas low pressure gap arrangement and the Mirathenerzeugung.
1977 The new oil distillation (Grimma
distillation) and the great experimental plant Salicyl acid waste water
disposal is put into operation.
1981 Introduction of the DK refinement and
introduction of the HCF procedure.
1982 The production profile changes in favour of
higher improved products and the rise of the interest of bright products.
The oil processing is intensified by the introduction of the reformer 3, the
Visbreakers and the renderer's distillation.
1984 The vacuum side gonorrhea to the production of a
raw material for the synthesis gas production and a Visbreaker-vacuum
distillate to the Hydrospalten is put into operation.
1985 Extension of the HCF procedure by a procedure
step to the catalytic Entparaffinieren by means of a Zeolithkatalysators.
1986 Introduction of a new investment complex to the
production of low pressure methanol of synthesis gas as a condition for a
refinery free of fuel oil.
1989 The political layout in autumn of the year takes
next time determining influence on the situation of the Leuna factory. The
suddenly carried out crossing to the market economy and the breakdown of the
GDR and east market leads to considerable financial losses and is the
starting point for a rapid employee's dismantling.
1990 Economic and social aspects give the rash for
the preservation of the location of Leuna. Nevertheless, it turns out fast
that the combine converted in a corporation can be received not on the whole.
1991 Up to the end of the year the structures and
arrangements are analyzed by order of the trust institution by famous firms
of consultants after free-enterprise points of view relevant for environment
and are valued. The privatisation strategies whose basic idea intends a
Splittung of the enterprise in survivable business segments are developed.
The Linde AG takes over the area technical gases.
1992 The contract between the trust institution and
the syndicate Societé Eleven Aquitaine/Thyssen commercial union about the
privatisation of the Leuna refinery is concluded. The new
Tankwagenbefüllstation is put into operation.
1993 The first privatisation in the chemical area on
the business segment amine and Dimethylformamid occurs through the Belgian
enterprise UCB. It follows the French Atochem with the traditional product
line urea to build formaldehyde and glues and the declaration of intent, in
a joint-venture with Air Liquide a new arrangement to the production of
hydrogen peroxide. The WIG Industrieinstandhaltung und Co. KG takes over the
former central technology of the LEUNA WERKE AG.
1994 The STEAG AG decides the construction of a new
natural gas power station as well as a gas and steam turbines arrangement.
The takeover and modernisation of the Caprolactamproduktion by the Belgian
DOMO Group shows an other future-protecting development for Leuna. The
InfraLeuna GmbH as a service provider and service partner of the chemical
producers is founded at the end of the year retrospectively to the 1st
January
1995 At the beginning of the year the to a great
extent progressed privatisations initiated by the trust institution of the
business segments Epoxydharze, catalysts, Tenside and the research are
finished. In May the laying of the foundation stone takes place for the
biggest German French capital project, the new refinery. The reconstruction
and extension of the DK refinement is concluded and a new refinery sewage
treatment (RAWA) is put into operation.
1996 The new sulfuric acid arrangement and the STEAG
power station go to company.
1997 The sales of the production plants for synthetic
wax on Ethenbasis to a middle-class enterprise group form the end of the
privatisation in the chemical area of the LEUNA WERKE AG. After
zweieinhalbjähriger construction time the most modern refinery of Europe is
put into operation in autumn by the Mitteldeutsche Erdöl-Raffinerie GmbH (MIDER).
2004 The main production lines of the LEUNA WORKS are
modernised and extended, new business segments have taken up the production.
More than 9 milliard DM of investments have protected the location of Leuna,
in eight famous French, Belgian, American and German enterprises chemical
products produce or protect the power demand. The location develops
increasingly to a chemical centre of European format which is prepared for
the requirements of the next decades. |